Bond Referendum 2016 Maintaining Excellence
Referendum Project Update1/26/2017On February 7th the Superintendent sent a letter home to all families with a general timeline for completion of the approved referendum projects. To see the projected general timeline by school please review the "Project General Timeline" web page.
Completed ProjectsMost projects have been completed between the end of the 2016-17 school year, Summer 2017, and during the first half of the 2017-18 school year. Several are currently in progress and a handful to begin in the Summer of 2018.- VES Installation of a Second Parking Lot Exit (COMPLETED 8/22/16)
- UMS Restoration of the Gym Floor (COMPLETED 8/12/16)
- OHES Replacement of the Media Center carpet (COMPLETED 8/15/16)
- MHS Installation of Walkway to Route 601 (COMPLETED 5/31/17)
- MHS Resurfacing the Track (COMPLETED 8/14/17)
- OHES Asphalt Replacement in Back Playground area (COMPLETED 8/17/17)
- UMS Media Center Renovations (COMPLETED 8/29/17)
- OHES Boiler Replacement (COMPLETED 8/17)
- OHES Kindergarten Bathroom Renovations (Partial Complete 8/17)
- OHES Both Gym Floors & Divider Replacement (Complete 9/17)
- VES Partial Roof Replacement (COMPLETED 8/17)
- LMS Media Center Carpet Replacement (COMPLETED 8/17)
- LMS Boiler/Chiller Replacement (COMPLETED 8/17)
- UMS Home Economics Room Conversion to Art Studio (COMPLETED 8/17)
- UMS Bathroom Renovations (COMPLETED 8/17)
- UMS Roof Replacement (COMPLETED 8/17)
- MHS Installation of Aspalt at Cougar Stadium Entrance (COMPLETED 8/17)
- UMS Gym Bleacher/Divider Replacement (COMPLETED 9/17)
- UMS Track Replacement (COMPLETED 10/17)
- OHES Roof Replacement (COMPLETED 10/17)
- LMS New Playground (COMPLETED 10/17)
- UMS Roof Replacement (COMPLETED 10/17)
- LMS Roof Replacement (COMPLETED 11/17)
- VES Music Room Alterations (COMPLETED 1/18)
Projects Under ConstructionProjects currently underway - Fall/Winter 2017